Sigma Optima, Incoplan, Advance Planning and scheduling software: Incoplan Interface
http://incoplan.blogspot.com/2010/02/incoplan-interface.html
Thursday, February 18, 2010. 2 How Data transfer happens. As the database of ERP can be different than database of Incoplan we need to extract the data from ERP to Incoplan Database. Both way exchange of data is possible. It means the interface can extract the data from the client ERP and insert the same in Incoplan database as well as it can post back the data to theb client ERP database. Interface acts as an independent entity controlling data traffic. 21 Ways of Data Transfer. 3 Data transfer frequency.
incoplan.blogspot.com
Sigma Optima, Incoplan, Advance Planning and scheduling software: Advantages of Incoplan over Project Management Software - Part I
http://incoplan.blogspot.com/2009/08/advantages-of-incoplan-over-project.html
Tuesday, August 4, 2009. Advantages of Incoplan over Project Management Software - Part I. Incoplan is an Advanced production planning and scheduling software. Incoplan can be effectively used to increase production uptime, improve shop floor predictability and reduce delivery times. Incoplan – Advanced Production Scheduling Software Solution:. Project Management Software (PMS):. Typical terminology used in industrial setup compared to project based environment:. Subscribe to: Post Comments (Atom). Http:...
incoplan.blogspot.com
Sigma Optima, Incoplan, Advance Planning and scheduling software: Material Constraint Theory - Last Part
http://incoplan.blogspot.com/2009/07/material-constraint-theory-last-part.html
Monday, July 27, 2009. Material Constraint Theory - Last Part. SOLUTION BY LINEAR PROGRAMMING. MANY TO MANY ALLOCATION PROBLEM. We can try to formulate the linear problem for this solution. With different objective functions. For current example, we can consider following three. A Maximize Profit and/or Priority. B Maximize Total production Quantity. C Minimize Total Delay [Cost / Time]. 8226; Parts to be produced are P1, P2 and P3. These are produced by operation 40, 50 and 60 respectively. All above se...
incoplan.blogspot.com
Sigma Optima, Incoplan, Advance Planning and scheduling software: Advantages of Incoplan over Project Management Software - Last Part
http://incoplan.blogspot.com/2009/08/advantages-of-incoplan-over-project_10.html
Monday, August 10, 2009. Advantages of Incoplan over Project Management Software - Last Part. Advantages of Incoplan over Project Management Software can be briefly explained as follows:. Project Management Software deals with “What resources are needed? 8221; It can swiftly reduce and increase resources. e.g. machines, tools etc. whereas Incoplan deals with “How to best Optimize the resources? Setup and run time. Incoplan has the in-built provision for adding setup time and run-time. In Project Manageme...
incoplan.blogspot.com
Sigma Optima, Incoplan, Advance Planning and scheduling software: Material Constraint Theory Part V
http://incoplan.blogspot.com/2009/07/material-constraint-theory-part-v.html
Friday, July 10, 2009. Material Constraint Theory Part V. VI) PROBLEM ILLUSTRATION – ONE TO MANY ALLOCATION. Find out total feasible quantity of item ‘A’, which is available for production at particular time ‘t’. Consider here, WIP and Store stock as well. Say it is Q[A]. Then there is no problem for inventory allocation, as sufficient quantity is available in stock to process succ op, without violating constraints defined. Else, problem B] will be applicable. 1] Current lot sizes of each of succ op,.
incoplan.blogspot.com
Sigma Optima, Incoplan, Advance Planning and scheduling software: Material Constraint Theory Part VI
http://incoplan.blogspot.com/2009/07/material-constraint-theory-part-vi.html
Monday, July 20, 2009. Material Constraint Theory Part VI. III ALLOCATION OF MATERIAL - “MANY TO MANY ALLOCATION”. Can we treat above problem as three dependent problems…? In two different manner …. TYPE I : One to Many assignment :. Number of problems is equal to number of current operations. TYPE II : Many to one assignment :. Number of problems is equal to number of successor operations. Let us analyze both the situation. TYPE I : One to Many assignment :. TYPE II: One to Many assignment:. 2] Interest...
incoplan.blogspot.com
Sigma Optima, Incoplan, Advance Planning and scheduling software: Material Constraint Theory Part IV
http://incoplan.blogspot.com/2009/07/material-constraint-theory-part-iv.html
Monday, July 6, 2009. Material Constraint Theory Part IV. V) HEURISTIC – MANY TO ONE ALLOCATION. 1] For given lot size of item L, calculate actual requirement of immediate Predecessor items. Q[i] = DL * x , q[j] = DL * y , q[k] = DL * k ,. 2] Calculate shortages for each predecessor item. Sq[i] = q[i] – Qi’’ , Sq[j] = q[j] – Qj’’ , Sq[k] = q[k] – Qk’’ ,. 3] Calculate the feasible quantity of each item that can be assign at particular time t, from store stock, based on stock policy. PQ[L-i] = TQ[i] / x ,.