wates-burgh-mill-gardens.blogspot.com
Burgh Mill Gardens
Monday, 22 April 2013. External groundworks are now underway with the installation of Drainage and Statutory services to the plots. Can we please ask all local residents to remind their children to not enter the site on a evenings and weekends. Thank you. Friday, 5 April 2013. Drainage works have progressed well this week, along with the commencement of the last two retaining walls which will then form the car park along the front of the flats. Wednesday, 13 March 2013. Monday, 4 March 2013. First fix bo...
wates-centenary-way.blogspot.com
Centenary Way
Monday, 23 December 2013. The Wates team and our sub-contractors would like to thank you for your continued patience whilst we have been on site at Centenary Way. Our site will close for the Christmas period on Tuesday 24 December, and will re-open in the New Year on Thursday 2 January. Can we also take this opportunity to wish you a Merry Christmas and a Happy New Year! Friday, 29 November 2013. Friday, 25 October 2013. Friday, 11 October 2013. Externally this week the bricklayers and renderers complete...
wates-field-head.blogspot.com
Field Head
Monday, 4 March 2013. The deep drainage is now complete and the Hydro Brake cast in-situ manhole is ready to be concreted. The car parking bays have been formed and the block Pavia to this area completed. Also prepared are the cycle shed base and the bin store base. The boundary wall has been constructed just leaving the tango fencing to be fixed to it. Friday, 15 February 2013. Our first floor flats are ready to be handed over to the decorators, just got to fill the systems with water and check for leak...
wates-foldings-avenue.blogspot.com
Foldings Avenue
Friday, 2 August 2013. Tuesday, 25 June 2013. Friday, 21 June 2013. We are only a few weeks from completion at Foldings Avenue, as you can see the internal finishes are 95% complete to both blocks, the external hard and soft landscaping is the current priority, however we a confident with a run of good weather this will be finished in the next week or so. Wednesday, 10 April 2013. Wednesday, 20 February 2013. Progress has been slow in January due to the adverse weather and cold temperatures, however Febr...
wates-former-fairfield-school.blogspot.com
Former Fairfield School
Thursday, 10 October 2013. We have come a long way since the blog has been down. With only weeks to go before handover the internal are almost complete. As you can see with the photos, the first and second floor are complete, only leaving the main entrance corridor to decorate. We are having the final push on the externals and the temporary car park being replaced back to the original state before we arrived. Monday, 22 July 2013. Friday, 5 July 2013. Friday, 21 June 2013. The second phase of External Wo...
wates-green-mount.blogspot.com
Green Mount
Tuesday, 6 August 2013. Mass concrete works have been completed to the retaining wall and the facing stonework has been laid ready for coping stones. Kerbing and hard landscaping works are progressing to the front of Block 1 and adjacent to Block 2. Friday, 21 June 2013. Excavations ,steel fixing and concrete pour for the retaining wall are now completed. The g. As trench is now excavated and g. As, water and electric are now connected to all plots. Monday, 22 April 2013. Monday, 8 April 2013. The stone ...
wates-hare-park-grange.blogspot.com
Hare Park Grange
Friday, 8 February 2013. The project is now complete after a seamless handover to Kirklees council on Thursday 7th February. The project was completed to a high quality standard both internally and externally with complimentary remarks from the client and clients representative. Another excellent project delivered from the Wates Kirklees Team. A big thankyou to all involved. Tuesday, 5 February 2013. Internally, we have nearly completed the snagging list produced by Kirklees Council. After the Christmas ...
wates-online.blogspot.com
WATES-ONLINE (BLOGnya CAK IMAM)
Recomment to Your Friends.
wates-project-house.blogspot.com
Project House
Wednesday, 18 September 2013. Friday, 23 August 2013. Externally British Gas laid the mains and fitted the meters. Northern power grid have commenced on site pulling the mains cable and next week will connect onto the existing services. Internally much the same as last week 2nd fix electrics fitting lights and sockets. Plumbers are connecting the sinks and fitting the showers in blocks 2 and 3, giving the plots a feel of completion with only the final decoration to do. Friday, 16 August 2013. On Block 1 ...
wates-projects.co.uk
DocElite by Finedata
Gloucestershire Police Authority Custody Centre). E-Mail : rob.brinsley@wates.co.uk. Telephone : 44 (0) 1454 615561. E-Mail : richard.turton@wates.co.uk. Telephone : 44 (0) 1454 615561. Click here to see other DocElite Portals. In order to use DocElite, you must have a valid User Name and Password. If you have them already, type them into the boxes below and click on the 'Enter DocElite'. DocElite has been tested and works with. Internet Explorer and FireFox.